Alan S. "The Leonardo spec for the 1MW plant says different....but it is of course, just a document"
Yes that is what was in the agreement. Notice that the "Water Pump Capacity" listed is 1500 kg/h which is 36000 kg/day in the report. Yes the value listed in the report was to be 10% less than what they claimed. So the pumps where pumping beyond their capacity.
But the point is, if they later ran with half of the ecats. then how could half of the pumps be still putting out the full 36000 kg/day as claimed? It seems like the most they could do would be about half of that or about 18000 kg/day.