Display MoreNote that Vaughn (and everyone else) refers to it as the "365 day test" or the "400 day test" ... omitting the word "Guaranteed".
Then in 214-25 Vaughn provides a timeline
NO mention of telling Rossi they didn't work ... or that the Guaranteed test was off. Early 2014 is spent preparing the Lugano reactors
Again, the word "guaranteed" is omitted, but it sure quacks like the GPT.
Here's an important point you may have overlooked: Vaughn is now talking about the '1 MW Plant'. This is NOT the 6 cylinder unit referred to in the 2nd amendment that Ampenergo refused to sign.
This matters because per Darden's testimony states that they were willing to pay for a 'test' (that Darden states emphatically was NOT a GPT), which Rossi proposed to Darden to do with the 1MW unit (which of course IH owned) in the form of the Term Sheet (and emails that strongly suggest that Rossi fraudulently represented regarding a 'real customer' who was actually himself).
We now have the evidence on the docket to know (if there was ever any doubt) that the Term Sheet was not and could not have been a GPT. It was a rental agreement. Re-read if you have any doubts about this.
It's important to 'watch the pea' in Rossi's shell game.